PURCHASE PROPERTY

ü Raise funds for down payment - completed 2017

ü Close on property - completed 2017

 ü Secure interim financing - completed 2017

 ü Create architectural renderings - completed 2018

 ü Obtain conditional use permit - completed 2018

 ⇒ Finance property - completed 2019

 ⇒ Update property for current use - completed 2019 

 

Construction Phase 1: RENOVATE & EXPAND EXISTING STRUCTURE

 Obtain conditional use permit - completed 2021

⇒ Raise funds for Phase 1 - in progress 2022

⇒ Civil engineering for Phase 1 - completed 2021 

⇒ Building Permitting for Phase 1 - completed 2022 

⇒ Rabbinic Oversight for Mikvah - in progress 2022 

⇒ Groundbreaking - completed JULY 6, 2022 

⇒ Construction for Phase 1 - in progress 2022

  • Basement Demo - complete July 2022
  • Sitework - in progress July-September 2022
  • Mikvah Pool Construction - in progress July-October 2022
  • Playground & Basketball Court - in progress August-October 2022
  • Hebrew School & Ilai's Library - projected Fall/Winter 2022
  • Mikvah Construction - projected Winter 2023
  • Kitchen Construction - projected Winter 2023
  • Main Level Improvements - Projected Spring 2023
  • Phase 1 Completion - Projected Spring 2023

CLICK HERE FOR PHOTOS OF THE CONSTRUCTION PROGRESS.

For future phases, please see the project overview